Typical price ranges
| Item | Typical range |
|---|---|
| Broom finish, 4 inch, per sq ft | $8 to $14 |
| Heavy duty, 5 to 6 inch with rebar, per sq ft | $10 to $16 |
| Stamped or colored, per sq ft | $12 to $22 |
| Tear out and haul off, per sq ft | $2 to $4 |
| Two car driveway, about 600 sq ft, broom | $5,000 to $8,400 |
| Single car extension or parking pad, about 200 sq ft | $1,800 to $3,200 |
| Apron in the county right of way | Priced on site |
Rough ranges for planning. Permits are extra and passed through at cost. Your exact price comes after a free site visit.
What moves the price
1. Tear out
Removing an old driveway means breaking it up, loading it and hauling it off. Thick or heavily reinforced old concrete takes longer. Expect roughly $2 to $4 per square foot on top of the new pour.
2. Thickness and steel
A 4 inch slab with fiber or wire mesh is fine for cars. If a full size pickup, RV or boat trailer will park on it, we go to 5 or 6 inches with a rebar grid. More concrete and more steel cost more, but a cracked driveway costs more than both.
3. The edge
We turn every driveway edge down to at least 6 inches. Edges are where tires roll off and where cracks start. It adds a little concrete and is one of the cheapest ways to make a driveway last.
4. Finish
A broom finish is the most economical. Stamped patterns and color take more labor, more material and a sealer, which is why stamped work runs $12 to $22 per square foot. A common middle ground is a broom field with a stamped or colored border. See our guide on stamped concrete versus pavers.
5. Grade, base and drainage
Hernando County soil is mostly sand over limestone. Sand drains well but has to be compacted. Lots that slope toward the garage, have soft spots or need fill brought in cost more to prep.
6. Access
If the concrete truck can back up to the forms, the pour is fast. If it cannot reach, we pump or wheel the concrete, which adds cost. We check access on every site visit.
7. Size
Setup costs are about the same for a small pad and a big driveway, so small jobs cost more per square foot.
8. Permits and the apron
Work in the county right of way, like the apron between your property line and the road, needs approval from Hernando County Public Works. Building permits depend on the job. Permit fees are extra and shown separately on our estimate. Our permit guide covers who issues what.
Three examples
Spring Hill tear out and replace
About 500 sq ft, 4 inch broom finish, 6 inch edge, old driveway removed. Roughly $5,000 to $9,000 depending on tear out and access.
Brooksville two car to three car
Add about 200 sq ft beside the existing driveway, doweled in with rebar. Roughly $1,800 to $3,200 plus any permit.
Hernando Beach boat pad
About 12 x 40 (480 sq ft), 6 inch with rebar for a loaded trailer. Roughly $4,800 to $7,700.
Examples are illustrations from the ranges above, not quotes for specific properties.
How to keep the cost down
- Pick a broom finish for the field and spend on a border instead of stamping the whole driveway.
- Clear vehicles, trailers and landscaping out of the way before pour day.
- Combine jobs. A driveway and a patio poured the same day share setup and the truck.
- Do not skimp on thickness where heavy vehicles park. Replacing a cracked slab costs more than doing it right once.
Next steps
See our concrete driveway service page for specs and FAQs, or our town pages for Brooksville, Spring Hill and Hernando Beach.