The specs at a glance
| Item | What we build |
|---|---|
| Field thickness | 4 inches for sheds and garages; 5 to 6 inches for shops, lifts and equipment |
| Thickened edge | At least 6 inches at the perimeter on every slab, deeper where the plans call for it |
| Steel | Welded wire mesh or a #3 or #4 rebar grid, with extra bars in the edge |
| Concrete strength | 3,000 psi minimum; 4,000 psi for shop floors, lifts and heavy equipment |
| Vapor barrier | 6 mil poly under enclosed buildings |
| Anchors | Bolts or straps set in the pour to the building company's layout |
| Square and level | Within the building company's tolerance so the walls sit flat |
Why the 6 inch thickened edge matters
The edge of a slab carries the walls, takes the hits from mowers and tires, and is where corners break off on cheap pads. Turning the edge down to at least 6 inches puts concrete where the load is. We do it on every slab, including small shed pads.
Anchors and Florida wind
Florida's building code requires buildings to resist hurricane wind loads, and most sheds, carports and metal buildings sold here come with a specific anchoring method. Some use wedge anchors drilled after the pour; many need bolts or straps set while the concrete is wet. Get the anchor layout from your building company before we pour.
What to get from your building company
- Outside dimensions of the slab (often a few inches bigger than the building)
- Edge depth and width, and any interior footings
- Anchor type, spacing and location
- Door openings, ramps or sloped entries
- Whether they need an inspection or photos before delivery
Permits and setbacks
Sheds, garages and shops have to sit a set distance from property lines, depending on your zoning. Small sheds can be exempt in some counties: Pasco exempts approved sheds of 150 square feet or less outside flood zones, while Sumter County's list stops at 100 square feet. Garages, shops and anything with footings usually need a permit. Qualifying farm buildings on agricultural land can be exempt under Florida Statutes 604.50. See our permit guide.
Typical costs
| Item | Typical range |
|---|---|
| Slab with 6 inch thickened edge, per sq ft | $10 to $15 |
| 12 x 16 shed pad | $1,900 to $2,900 |
| 24 x 24 garage slab | $5,800 to $8,600 |
| 30 x 40 shop slab | $12,000 to $18,000 |
Rough planning ranges, not quotes. Clearing, fill, deeper footings, access and permits change the price.
Cure time before delivery
Most sheds and carports can be set after about 7 days. Heavy buildings, car lifts and equipment should wait closer to 28 days, when concrete reaches its design strength. We tell you the right wait for your mix and the weather.
Ready to price one? See slabs and pads and footings and foundations, or the town pages for Brooksville, Masaryktown, Dade City and Zephyrhills.